Project Brief

Document Sign Off

Name Project Role Date Signed Off
Dawn Dodd Project Sponsor (50%) (Project Team Member) 12/09/2018 (Verbally signed off) 
Catherine Hetherington   Project Sponsor (50%) (Project Team Member) 12/09/2018 (Verbally signed off)
Richard Bailey Project Manager (Project Team Member) 12/09/2018 (Verbally signed off)
Colin Watt Programme Manager 12/09/2018 (Verbally signed off)
Alex Carter   Senior Supplier 12/09/2018 (Verbally signed off)
Willie Mitchell Business Lead (Project Team Member) 13/09/2018
Robert Gormley  Senior User (Project Team Member) 14/09/2018
Iain Fiddes Head of Development Services 12/09/2018
Mark Lang Development Technology Team Manager 12/09/2018
Adam Wheavil Production Management Applications Team Manager 21/09/2018
Heather Larnach Technology Management Team Manager 21/09/2018
Alister Webb Technical Lead Development Technology (Project Team Member) 14/09/2018
Mark McGowan Technology Management Technical Lead (Project Team Member) 13/09/2018
Andrew Gleeson Production Management Lead (Project Team Member) 13/09/2018

 

Date                   

Version      

Author                       

Section                     

Amendment                              

27/08/2018

Draft v1.0

Richard Bailey

All

Initial draft for review / discussion 

10/09/2018 Draft v1.1 Richard Bailey All Amends after initial comments and updated ready for circulation / sign off  

Project Info

Project
UniDesk for UHI
Code
SMI019
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Dawn Dodd
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Aug-2018
Planning Date
14-Sep-2018
Delivery Date
17-Jun-2019
Close Date
05-Jul-2019
Overall Priority
Higher
Category
Discretionary