This project is to transition the JournyX platform to a formally supported service on an up to date technology platform.

Mark Ritchie is leading as Sponsor in absence of Head of Service Management.

PM has agreed with Sponsor that a pre-planning stage be carried out - this will include production of a paper outlining options and costs in order to reach a decision on the scope of the project, before formal planning; End of Planning has therefore been pushed back to 29/04/19. 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2021 BLUE 121.0 days 0.0 days 0.0

Project Info

Project
JournyX Service
Code
SMI022
Programme
ISG - IT Service Management (SMI)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Mark Ritchie
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
04-Mar-2019
Planning Date
22-May-2020
Delivery Date
01-Oct-2020
Close Date
14-May-2021
Overall Priority
Normal
Category
Compliance