April 2021
- Report Date
- April 2021
Achievements in Last Period
- Project planning has progressed but has not been completed due to resource availability.
- Planning signoff now expected w/c 03/05/21.
- Initial Jiras have been prioritised and estimated.
Issues
- Resource conflicts (Service Management resource availability). It has now been confirmed that 1d per week effort to be ringfenced for the project.
Next Steps
- Complete planning
- Work through prioritised jiras (initial focus quick calls api lookup, data imports)
Milestones
To be confirmed as part of planning:
End of Planning | 29-Apr-2021 |
Agree DNS Migration plan | 19-May-2021 |
Quick Calls API Lookup | 21-May-2021 |
Quick Calls Jiras (1) | 28-May-2021 |
UniDesk DNS Migration | 18-Jun-2021 |
Review Data Import process | 23-Jun-2021 |
Decision on Database Consolidation and Decommissioning | 25-Jun-2021 |
Quick Calls Jiras (2) | 25-Jun-2021 |
DSOR | 16-Jul-2021 |
Quick Calls Jiras (3) | 16-Jul-2021 |
Project Closure | 30-Jul-2021 |
- Approved budget
- 0.0 days
- Activity this month
- 9.6 days
- Activity this year
- 17.5 days
- Activity to date
- 17.5 days
- Estimate to complete current year
- 34.1 days
- Estimate to complete future years
- 0.0 days