Q2

Report Date
February 2018

Workshop with key stakeholders from the SRS Committee took place in November. Following this, draft content for the document was updated to incorporate feedback. Further work is continuing to develop the draft further. Work has been undertaken to develop strands of the new strategy including staff volunteering and the student experience. Aiming to circulate a full draft of the strategy to key stakeholders in Q3 (including asking for views at the Sustainability Awards Ceremony).

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SRS Strategy Review
Code
SRP003
Programme
SRS - Reporting & Strategy (SRP)
Project Manager
Matthew Lawson
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
02-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal

Documentation

Not available.