Q3

Report Date
May 2018

The draft strategy has been revised and reframed, receiving positive feedback from stakeholders. Work has been undertaken to ensure alignment with Waste Strategy, Widening Participation Strategy and developments with staff volunteering. Updated version to be circulated with senior management in May, to ensure buy in before the SRS Committee in June. 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SRS Strategy Review
Code
SRP003
Programme
SRS - Reporting & Strategy (SRP)
Project Manager
Matthew Lawson
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
02-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal

Documentation

Not available.