Q1 18/19

Report Date
November 2018

More time to progress this from January 2019, when the capacity of the community engagement team within SRS will increase. Project still being driven by Procurement. Next step is to simplify menu for suppliers and to progress projects with Balfour Beatty.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Community Benefit Procurement Clause
Code
SRSCE-B
Programme
SRS - Community Engagement (SRS)
Project Manager
Sarah Anderson
Project Sponsor
Michelle Brown
Current Stage
Initiate
Status
In Progress
Start Date
02-Feb-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
Category
Discretionary

Documentation