Q1 18/19

Report Date
November 2018

Increased capacity from early 2019 should make it possible to progress.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Community Access to Rooms
Code
SRSCE-S
Programme
SRS - Community Engagement (SRS)
Project Manager
Sarah Anderson
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
Suspended
Start Date
02-Feb-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.