PT: Student functions and enhanced staff functions now live, delay to delivery of full staff functions

Report Date
August 2012

Achievements in Last Period

Project aims for August were to:

  • define the requirements for the (enhanced) notes functions, in particular the email notifications (complete)
  • complete build and test for student MyEd channel changes (complete)
  • build, test and release enhancements to notes as soon as they are ready in priority order 1. Mark as read (complete), 2. Notification emails (complete), 3. Add file (in progress), 4. Flag as deleted (in progress), 5. Summary digest email to monitor (not started) [note it is unlikely all of these will be completed in September]
  • track user feedback and suggestions and define changes to be grouped into mini-project for small enhancements (see Staff Enhancements List)
  • participate in the wider communications planning (complete)
  • participate in the training and rollout where needed (complete).

Issues

  • Amber status due to: delay in completion of work in July and August meant prioritisation of student functions for delivery prior to Fresher's week (complete); delivery of remaining staff functions will be through September.
  • Introduction of new functionality to enable formatting of text will delay delivery of Add File, Flag as Deleted and Summary digest email to monitor, likely into October.

Next Steps

Project aims for September are to:

  • deploy the student MyEd channel changes to live
  • complete build and test of the remaining PT and SSO functions (including batch job of notification for change of PT) and deploy to live
  • build, test and release enhancements to notes as soon as they are ready in priority order (new function formatting added following core group decision on 10-Sep-12) 1. Formatting of text within notes, 2. Add file (in progress), 3. Flag as deleted (in progress), 4. Summary digest email to monitor (not started) [note it is unlikely all of these will be completed in September]
  • continue to track user feedback and suggestions and define changes to be grouped into mini-project for small enhancements (see Staff Enhancements List)
  • participate in the development of the communications to staff and students and updates regarding the IT Tools project.

Milestones and tracking of completion are on the wiki page: Project Milestone and Completion Log

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
385.0 days
Activity this month
65.0 days
Activity this year
65.0 days
Activity to date
251.0 days
Estimate to complete current year
126.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Initial ESS IT Tools (Phase 1)
Code
SSG001
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Sheila Fraser
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
27-Mar-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Feb-2013
Overall Priority
Higher
Category
Discretionary