October 2012
- Report Date
- October 2012
Report by Sheila Fraser for October 2012
Achievements in Last Period
Project aims for October were to:
- complete the acceptance test of the remaining PT and SSO functions (including batch job of notification for change of PT) and deploy to live (complete, except for 'Support Team' link details)
- complete the acceptance test and deploy to live enhancements to 2. Add file (in progress), 3. Flag as deleted (in progress) (complete)
- continue to track user feedback and suggestions and define changes to be grouped into mini-project for small enhancements (see Staff Enhancements List) (complete)
- complete the handover to support and move to closure (closure expected early November) (handover to support progressed, one item to complete for closure)
- initiate the project for the small enhancements (and ask Senior Tutors to prioritise the requirements) (complete)
- initiate the projects for the Small Group functions, Photos, and ability to add the meeting to the staff and student diaries (completed on 02-Nov-12)
Issues
Next Steps
Project aims for November are to:
- complete the remaining 'Support Team' link details build, test and deploy to live
- complete the handover to support and close the project (closure expected end November)
Target date | Title |
---|---|
30-Nov-2012 | Project Closure |
- Approved budget
- 339.0 days
- Activity this month
- 24.0 days
- Activity this year
- 129.0 days
- Activity to date
- 315.0 days
- Estimate to complete current year
- 18.0 days
- Estimate to complete future years
- 0.0 days