January 2013

Report Date
January 2013

Achievements in last period

Project aims for December were to:

  • Complete the remaining 'Support Team' link details test and deploy to live - built and tested, will be deployed to LIVE after LIVE SITS upgrade
  • Complete the handover to support - complete
  • Draft and agree the completion report and close the project - feedback incorporated, closure not completed largely due to pressure on PM time; expected to complete in February.

Issues

  • None

Next steps

  • Move deployment of 'Support Team' details to SSG004 to coincide with other new functions that will be deployed at the same time
  • Close project

 

Target dateTitle
19-Feb-2013Project Closure

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
153.0 days
Activity this month
9.0 days
Activity this year
143.0 days
Activity to date
330.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Initial ESS IT Tools (Phase 1)
Code
SSG001
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Sheila Fraser
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
27-Mar-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Feb-2013
Overall Priority
Higher
Category
Discretionary

Documentation