Weekly Report - week ending 3/5/13
Enhancement of Student Marketing Services
SSG003
Project Weekly Status Report
SSG003 Project | |||||
Week ending: | Friday 3rd May | ||||
Project headlines: |
| ||||
Summary status: | Overall | Schedule | Budget days taken vs. actual | Delivery of Scope | |
Green | Green | Green 63 days taken (was 58) 17 to complete (was 21)
Weekly Apps Effort - 5 days Reduction in ETC - 4 days Contingency - 20 days
|
Green
| ||
Project issues and risks for attention of the Board (includes all open issues and any which have changed status
No medium or high risks https://www.projects.ed.ac.uk/project/ssg003/risks
All Issues https://www.projects.ed.ac.uk/project/ssg003/issues
|
Project activities | ||
Planned activities completed this week:
| Resolve the Funding Issue | |
Planned activities not completed this week: |
| IMPACT & ACTIONS |
| All actvities completed
| |
Activities planned for next week (week ending 3rd May) |
Start Build, Complete by 23rd May Task List - https://www.wiki.ed.ac.uk/display/SMSIME/SSG002%2CSSG003+Tasks+Schedule | |
Any other points of note: With funding additional 20-25 days agreed for total SSG002/3 we are confident of completing remaining PG work within budget. New milestones in place Build ends by 24th May UAT from Monday 27th through to 7th June Acceptance Sign-off 11th June Deliver to Live 13th June Deployment sign-off 20th June Closure 27th June
|