Weekly Report - week ending 3/5/13

Enhancement of Student Marketing Services

SSG003

 Project Weekly Status Report

 

SSG003 Project

Week ending:

Friday 3rd May

Project headlines:

  • UG Enhancements Live
  • PG Build starts Monday 6th

Summary status:

Overall

Schedule

Budget days taken vs. actual

Delivery of Scope

Green

Green

Green

63 days taken (was 58)   17 to complete (was 21)

 

 Weekly Apps Effort - 5 days Reduction in ETC - 4 days

Contingency - 20 days

 

 

 

 

 

 

 

 

 

Green

 

 

 

 

      

 

Project issues and risks for attention of the Board (includes all open issues and any which have changed status

 

No medium or high risks

https://www.projects.ed.ac.uk/project/ssg003/risks

 

All Issues

https://www.projects.ed.ac.uk/project/ssg003/issues

 

 

 

 

 

 

 

Project activities

Planned activities completed this week:

 

 

Resolve the Funding Issue

Planned activities not completed this week:

 

IMPACT & ACTIONS

 

 

 

 

 

 

All actvities completed

 

 

Activities planned for next week (week ending 3rd May)

 

Start Build, Complete by 23rd May  

Task List - https://www.wiki.ed.ac.uk/display/SMSIME/SSG002%2CSSG003+Tasks+Schedule

  

 

Any other points of note:  

With funding additional 20-25 days agreed for total SSG002/3 we are confident of completing remaining PG work within budget.

New milestones in place Build ends by 24th May UAT from Monday 27th through to 7th June Acceptance Sign-off 11th June Deliver to Live 13th June Deployment sign-off 20th June Closure 27th June

 

 

 

 

 

 

 

 

 

 

 

 

 

Project Info

Project
Enhancement of student marketing services
Code
SSG003
Programme
Student Services (STU)
Project Manager
Maurice Franceschi
Project Sponsor
John Cavani
Current Stage
Close
Status
Closed
Start Date
27-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary