During the Initial ESS IT Tools project many of the requirements were unclear. As use of the wider Personal Tutor System starts to grow, a number of improvements to the Initial IT Tools have been suggested. This project is to implement as many of the suggested enhancements as can be accommodated within the budget.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
June 2013 | BLUE | 0.0 days | 0.0 days | 0.0 |