Organisation
Work/Task Breakdown
This project will be run in a manner similar to the support model, with small changes being released as they are tested and accepted as ready to go live.
Develop project brief - Project Services
Develop prioritised list in conjunction with users - SACS BPE and Project Services
Clarify requirements - Development Team and Config Team to propose solutions to SACS BPE in conjunction with users / enhancement suggester - SACS to confirm requirements
Develop functions to fulfil prioritised requirements - Applications Management with support from Development Team and Configuration Team as required
Test and sign-off requirements - SACS BPE in conjunction with users / enhancement suggester
Deploy functions to LIVE - Applications Management / Development Technology
Ensure functions are applied as the same version of code across DEV, TEST and LIVE environments - Applications Management
Resources Skills and Cost
This project was agreed on the basis of 40d of project work for the suggested small enhancements, which will be primarily split between the Development Team and Configuration Team (as technical leads, dependent on technical area) and Applications Management. 6d of Project Services time for Project Management is also allocated to the project.
Team | Estimate (d) |
Development Team | 4 |
Applications Management | 22 |
Configuration Team | 7 |
Development Technology | 2.5 |
Project Services | 6 |
Contingency & Closure | 4.5 |
Total | 46 |
Note the above breakdown is based on the prioritised requirements, signed off by Ian Pirie Project Sponsor.