Report for April 2013
- Report Date
- April 2013
Achievements in Last Period
Project aims for April were to:
- Achieve acceptance sign-off for all of E#7, E#60, E#120, E#59 & 77, E#93, E #64a/64b and deploy to LIVE at same time as SSG007 Small Group Functions.
- Start project closure
Issues
- N/A
Next Steps
- Complete deployment of changes to TRN
- Complete project closure (draft complete, awaiting final completion of TRN change)
Target date | Title |
---|---|
24-May-2013 | Project Closure |
- Approved budget
- 46.0 days
- Activity this month
- 3.6 days
- Activity this year
- 44.3 days
- Activity to date
- 44.3 days
- Estimate to complete current year
- 1.6 days
- Estimate to complete future years
- 0.0 days