During the Initial ESS IT Tools project many of the requirements were unclear. As use of the wider Personal Tutor System starts to grow, a number of improvements to the Initial IT Tools were been suggested. This project is to implement one particular prioritised suggestion, that when the meetings are saved in the IT Tools they are also able to be saved into the staff and students electronic diary.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2013 BLUE 34.0 days 34.0 days 0.0

Project Info

Project
ESS Meetings in Calendar
Code
SSG005
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Sheila Fraser
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
04-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Apr-2013
Overall Priority
Higher
Category
Discretionary

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.