February 2013

Report Date
February 2013

Achievements in Last Period

Project aims for February were to:

  • Complete Acceptance Sign-off Review in TEST - complete
  • Deploy to LIVE - complete
  • Deployment sign-off review - incomplete, see issues.

Issues

  • Following deployment an issue has been raised of some users receiving blank emails. However, it has not yet been possible to reproduce this issue. If this cannot be reproduced then we will be able to proceed to deployment sign-off review, if it can be reproduced then we may need to implement a fix.
  • The above, and the need to deploy to train, mean the project effort may go above the estimate.

Next Steps

Project aims for March are to:

  • Complete deployment sign-off review.
  • Deploy to SITS train environment.
  • Project closure.

 

Target dateTitle
14-Feb-2013Deploy to LIVE
28-Feb-2013DSOR ESS Meetings in Calendar
14-Mar-2013Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
34.0 days
Activity this month
4.0 days
Activity this year
32.0 days
Activity to date
32.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ESS Meetings in Calendar
Code
SSG005
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Sheila Fraser
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
04-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Apr-2013
Overall Priority
Higher
Category
Discretionary