February 2013
- Report Date
- February 2013
Achievements in Last Period
Project aims for February were to:
- Complete Acceptance Sign-off Review in TEST - complete
- Deploy to LIVE - complete
- Deployment sign-off review - incomplete, see issues.
Issues
- Following deployment an issue has been raised of some users receiving blank emails. However, it has not yet been possible to reproduce this issue. If this cannot be reproduced then we will be able to proceed to deployment sign-off review, if it can be reproduced then we may need to implement a fix.
- The above, and the need to deploy to train, mean the project effort may go above the estimate.
Next Steps
Project aims for March are to:
- Complete deployment sign-off review.
- Deploy to SITS train environment.
- Project closure.
Target date | Title |
---|---|
14-Feb-2013 | Deploy to LIVE |
28-Feb-2013 | DSOR ESS Meetings in Calendar |
14-Mar-2013 | Project Closure |
- Approved budget
- 34.0 days
- Activity this month
- 4.0 days
- Activity this year
- 32.0 days
- Activity to date
- 32.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days