March 2013

Report Date
March 2013

Achievements in Last Period

Project aims for March were to:

  • Complete deployment sign-off review - complete.
  • Project closure - partially complete: sign-off complete, QA through WIS remaining.

Issues

  • N/A.

Next Steps

Project aims for April are to:

  • Complete final closure activities - QA through WIS.

 

Target dateTitle
29-Mar-2013Project Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
34.0 days
Activity this month
1.0 day
Activity this year
33.0 days
Activity to date
33.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
ESS Meetings in Calendar
Code
SSG005
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Sheila Fraser
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
04-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Apr-2013
Overall Priority
Higher
Category
Discretionary