Project Activity - w/c 15th & 22nd April
- 15/4 - Agreed project would be suspended for 1 month with Programme manager and sponsor; request sent to WIS on 19/4; not approved as requested confirmation of dates for replan
- 22/4 - Agreed with programme manager that project would be suspended for 3 months (original request to close revised to be suspension); request sent to WIS. Confirmation sent to Sponsor, project team and Bill Lee (re Peter Pratt's resource). Await confirmation from WIS.