Organisation

 

Work / Task Breakdown Structure 

Task

Deliverable

Owner

Project Management

Project authorisation, Brief and Project documents. Communication and coordination with stakeholders.

Project Services

Build It

Business Analysis (BRD)

System Analysis (SDS)

Build solution and peer test

Chris Giles with Dev Team/Config Team

Dev Team/Config Team with Chris Giles

Dev Team/Config Team

Check It

UAT Test plan

Test solution

 

Chris Giles

SACS  and user group

Dev Team/Config Team  support

Document

Handover to support

Dev Team, Apps Man

Release

Deploy

Dev Tech, Apps Man

Close It

Closure Review

Project Services

 

 

Resources, Skills and Costs

Currently, the total costs for Phase 1-3 of this initiative is estimated as: 188.7 days (the full breakdown by task, phase and team can be found in the 3 point estimate), which includes 178.3 days for IS Applications. As the Project budget is capped at 100 days for IS Applications, the scope will comprise the Phase 1 deliverables only - ensuring students can view photos of the relevant staff within the Personal Tutor system.

The estimates for Phase 1 delivery, by team are as follows:

Breakdown by TeamPhase 1 only
Apps Mgmnt8.9
Config Team (SITS)10.3
Dev Team36.8
Dev Tech15.6
Director's Office1.3
Project Services30.4
Tech Mgmnt2.2
Contingency1.5
TOTAL IS107.0
SACS10.4

At mid year planning, the forecast planning split allows for 13 days activity in 2013/14. The current forecast plan meets this target. 

Project Info

Project
ESS Photos (for students)
Code
SSG006
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
Laura Bell
Project Sponsor
Ian Pirie
Current Stage
Close
Status
Closed
Start Date
12-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
15-May-2013