Report for January 2013
- Report Date
- January 2013
Achievements in Last Period
Prioritisation survey results collated and phased approach agreed with Senior supplier
Issues
Next Steps
Target date | Title |
---|---|
17-Jan-2013 | Business Requirements Review |
22-Feb-2013 | Project Brief |
Estimates and Project Brief completed and signed off by project team
Further options for opt in/ opt out solutions raised; discussions held with key stakeholders and scope/ approach for Phase 1 further defined, with a likely reduction in estimates.
Transition to new Project Manager in progress.
Estimates for Phase 1 to be reviewed given potential reduction in scope agreed in principle with Project Sponsor, so milestone for completion of the Project Brief will need to be revised.
Approach for Phase 1 is dependent on confirmation with Card Services - discussions underway.
Confirm proposed Phase 1 approach is viable with Card Services.
Revise estimates, plans and scope in brief.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days