Report for February 2013
- Report Date
- February 2013
Achievements in Last Period
- Transition to new project manager completed
- Project brief re-drafted; estimates revised following survey results and new technical solution; revised project plan developed
- Brief walk through scheduled with sponsor in preparation for final sign off on 8th March
- Revised approach reviewed and agreed with Card Services
Issues
- Funding cap for the project is 100 days; forecast estimate around 107 days.
Next Steps
Target date | Title |
---|---|
08-Mar-2013 | Project Brief - Phase 1-3 |
29-Mar-2013 | Ph.1 PPAR: Analysis Review |
26-Apr-2013 | Ph.1 PPDR: Design review |
14-Jun-2013 | Ph.1 PPBR: Build Review |
28-Jun-2013 | Ph.1 PPIR: Integration Review |
18-Jul-2013 | Ph.1 ASOR: Acceptance Review |
09-Aug-2013 | Ph.1 Deploy to Live |
23-Aug-2013 | Ph.1 DSOR: Deployment Review |
28-Aug-2013 | Phase 1 Closure |
- Approved budget
- 100.0 days
- Activity this month
- 7.8 days
- Activity this year
- 17.9 days
- Activity to date
- 17.9 days
- Estimate to complete current year
- 75.7 days
- Estimate to complete future years
- 13.3 days