Report for March 2013
- Report Date
- March 2013
Achievements in Last Period
- Project Brief signed off; with caveat of potential Risk around Configuration resources
Issues
- SSP/ SACs Risk 4 has become an issue; and the scope of all work by the SSP team is under review.
- During March the SSIG Board Meeting, SSP/ SACS Risk 4 was discussed and it was agreed that this project, as the 4th of 5 priorities for ESS Programme, would be at risk of suspension until confirmation is received that the appropriate resources are available for the project to be delivered.
- Therefore, the project status is Amber until confirmation that the resources to support the Project are in place to support delivery in 2012/13 is received.
Next Steps
- The SSP/ SACs Programme manager will work with the resource managers to agree the scope of SSP/ SACs projects which can be delivered in 2013/14 and confirm if SSG006 needs to be suspended as a result.
Target date | Title |
---|---|
26-Apr-2013 | Ph.1 PPAR: Analysis Review |
16-May-2013 | Ph.1 PPDR: Design review |
14-Jun-2013 | Ph.1 PPBR: Build Review |
- Approved budget
- 100.0 days
- Activity this month
- 2.5 days
- Activity this year
- 20.5 days
- Activity to date
- 20.5 days
- Estimate to complete current year
- 69.2 days
- Estimate to complete future years
- 17.2 days