September 2013
- Report Date
- September 2013
Achievements in Last Period
- Started build for post go Live enhancements
Issues
- There has been delays in starting the build for post go Live enhancements, due to resource priority on SSP project SAC015, and disruption of the EUCLID Development (DEV) environment during its refresh from Live (as part of SAC024 SITS upgrade). This will cause the deployment to Live to be delayed by 4 weeks to 28/10 (was planned for 1/10).
Next Steps
- Complete post go live deployment
28-Oct-2013 | Deploy post live fix |
12-Nov-2013 | DSOR: Deployment sign off |
22-Nov-2013 | Close |
- Approved budget
- 11.5 days
- Activity this month
- 2.3 days
- Activity this year
- 5.5 days
- Activity to date
- 79.2 days
- Estimate to complete current year
- 13.2 days
- Estimate to complete future years
- 0.0 days