Report for August 2012
- Report Date
- August 2012
Achievements in Last Period
- ColdFusion 9 version of CCTS application promoted to TEST environment
- Outstanding milestones revised and submitted to WIS for approval
Issues
- None
Next Steps
- Careers staff to complete user testing
- Upgraded version of application to be applied to LIVE
Target date | Title |
---|---|
12-Sep-2012 | Acceptance Sign Off Review |
19-Sep-2012 | Deployment |
26-Sep-2012 | Deployment Sign Off Review |
28-Sep-2012 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days