To deliver small-scale enhancements to the EUCLID student record system application (Internally driven by process improvement)
this will be delivered in multiple phases , each phase will have its own business requirements document (BRD) written by SACS Registry,
IS Apps will deliver SITS configuration to meet the business requirements.
This project will be delivered in multiple phases , each phase will have its own BRD and milestones into TEST and LIVE.
Update 6-Feb 2013
Project closed
Deployment Milestones previously achieved:
Phase 1 - UKBA ELTC Students - LIVE - 31-Aug-11
Phase 2 - Discounts - LIVE - 11-July-12 Phase 3 - PGT RPL - EUCLID Changes - LIVE 29/9/11 Phase 3 - PGT RPL - BOXI Changes - LIVE 10/11/11
Phase 8a - Core Registry function enhancements- LIVE 28-Aug-12
Phase 8b - Assumed Exited & Ceremony removal - LIVE - 10-July-12 Phase 10a -Exam Marks XML upload - LIVE 29-Mar-12
Phase 10b - Marks Upload Validation - LIVE 22-Nov-12
Phase 11 - Matriculation changes - LIVE - 10-July-12
Phase 13 - Agents - LIVE - 4-Dec-12 Phase 14 - Role Group Hierarchy - LIVE 1-Nov-11 Phase 15 - Fund Management decoupling from SRS17 - EUGEX views - LIVE 13-Dec-11 Phase 15 -Fund Management decoupling from SRS17 - Registry Universe- LIVE 13-Feb-12 Phase 15 - Fund Management decoupling from SRS17 - EUGEX & ESSMU - LIVE 7-Mar-12
Phase 17 - PPMD - in TEST - LIVE 10-Oct-12
Phase 19 - Automate VCR creation - in TEST - LIVE 11-Oct-12
N.B. this project was started before the move to the new projects website, so documentation is only shown from 6th August 2012. Documentation prior to this can be found on the old site at http://www.old.projects.ed.ac.uk/areas/student/sacs/STU213/index_table.shtml
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
January 2013 | BLUE | 259.0 days | 259.0 days | 0.0 |