Programme Report for August 2012
- Report Date
- August 2012
Achievements in Last Period
- Acceptance stage signed off at ASOR and plans made for deployment
- All outstanding JIRAs completed and tested before returning to users
- Upgraded version promoted to LIVE on 16/08/12
- Solution for "apostrophe issue" applied to TEST and test downloads sent to Registry for testing
- Deployment stage signed off
Issues (resolved)
- No feedback received on deployment (because of staff unavailability) so deadline for DSOR extended
- New milestones for DSOR and Closure submitted to WIS for approval
Next Steps
- Project closure documentation to be prepared and submitted
Target date | Title |
---|---|
19-Sep-2012 | Closure |