Report for March 2014
- Report Date
- March 2014
Achievements in Last Period
- Issue with data feed resolved in DEV & TEST
- Remaining milestones updated and agreed
Issues
- Data feed not working correctly [resolved]
Next Steps
- Final sign-off of TEST feed
- Promote website and data feed to LIVE
Milestones
10-Apr-2014 | ColdFusion Web Service Test Sign-Off | Accept |
15-Apr-2014 | Deployment to LIVE | Deliver |
24-Apr-2014 | Project Closed | Close |
- Approved budget
- 28.0 days
- Activity this month
- 2.3 days
- Activity this year
- 13.4 days
- Activity to date
- 27.1 days
- Estimate to complete current year
- 1.3 days
- Estimate to complete future years
- 0.0 days