Project Activity - w/c 3rd June |
- Held meeting with key representatives to discuss test environment options
- Estimates agreed with Apps Mgt; walk through with Dev Tech, Tech Mgt and Dev to agree dependencies, tasks and responsibilities; estimates due 12/6
- Review of test environment options with Service Mgt
- Review of test environment options with Dev Tech.
|
Laura Bell |
10-Jun-2013 |
Project Activity - w/c 27th May |
- Notes from initial kick off meeting drafted and circulated
- Sessions to review estimates scheduled to gather estimates
- Session booked to review test environment approach in more depth
- Risks updated on Projects website
|
Laura Bell |
03-Jun-2013 |
Project Activity - w/c 20th May |
- Draft Project Brief completed (except milestones)
- Meeting with Service Management to discuss the overall concept and key issues
- ASTA updated with proxy budget as holding position
- Papers prepared for Project Kick off/ Initiation meeting to discuss current issues
- Issues with Infrastructure/ future Office 365 strategy discussed with Technology Management manager
|
Laura Bell |
24-May-2013 |
Project Activity - w/c 13th May |
- PM familiarised with the project aims, scope, background and stakeholders
- Resource requests issued to managers to support estimating session
- Estimation session booked
- Business analyst brief to start analysis
|