Project Activity - w/c 27th May

  • Notes from initial kick off meeting drafted and circulated
  • Sessions to review estimates scheduled to gather estimates
  • Session booked to review test environment approach in more depth
  • Risks updated on Projects website

Project Info

Project
Office 365 Integration for Timetabling
Code
STU231
Programme
Timetabling (TTU)
Project Manager
David Watters
Project Sponsor
Susan Rigby
Current Stage
Close
Status
Withdrawn
Start Date
10-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
2
Overall Priority
Normal
Category
Discretionary