Project Activity - w/c 3rd June

  • Held meeting with key representatives to discuss test environment options
  • Estimates agreed with Apps Mgt; walk through with Dev Tech, Tech Mgt and Dev to agree dependencies,¬†tasks and responsibilities; estimates due 12/6
  • Review of test environment options with Service Mgt
  • Review of test environment options with Dev Tech. Tech Mgt and Dev
  • Proposed scope agreed
  • Timeline for Test Tenancy agreed with Service Mgt (process underway; 2-4 weeks to complete with MS)
  • Dependency on COM001 clarified/ timeline for delivery clarified
  • New server requirement identified
  • Project report completed

Project Info

Project
Office 365 Integration for Timetabling
Code
STU231
Programme
Timetabling (TTU)
Project Manager
David Watters
Project Sponsor
Susan Rigby
Current Stage
Close
Status
Withdrawn
Start Date
10-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
2
Overall Priority
Normal
Category
Discretionary