Report for April 2014

Report Date
April 2014

Achievements in Last Period

  • PICCL on extra effort submitted to WIS and accepted by them
  • Decision made to withdraw project

Issues

  • Discussions on project status to determine whether to continue with project or not

Next Period 

  • Project to be suspended

 

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
188.0 days
Activity this month
0.0 days
Activity this year
160.1 days
Activity to date
187.3 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Office 365 Integration for Timetabling
Code
STU231
Programme
Timetabling (TTU)
Project Manager
David Watters
Project Sponsor
Susan Rigby
Current Stage
Close
Status
Withdrawn
Start Date
10-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
2
Overall Priority
Normal
Category
Discretionary