Report for July 2014

Report Date
July 2014
 

Achievements in Last Period

  • Project has been withdrawn (and closed)
Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
205.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
189.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Office 365 Integration for Timetabling
Code
STU231
Programme
Timetabling (TTU)
Project Manager
David Watters
Project Sponsor
Susan Rigby
Current Stage
Close
Status
Withdrawn
Start Date
10-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
2
Overall Priority
Normal
Category