Sponsor - PM - Procurement Meeting 23/5

As discussed, decisions and actions ..

 

1)  I do not see a strategy document for RMAS, so if George could send me it I will start on this. DONE

 

2) George to send me timeline for Restricted Procurement so I can set out milestones for us. DONE

 

3) Graham to be set up on INTEND

 

4) Sue, Graham and Maurice will set out a first draft of how we will split up Quality into main headings and weightings.

 

5) We will have hands-on feedback into evaluation, as well as Presentation feedback in ITT scoring.

 

6) Price/Quality ratio is 20/80

 

7) George to be invited to presentations next week

Project Info

Project
OLLIE & CUPID Replacement - Procurement
Code
STU232
Programme
CAHSS Portfolio Projects
Project Manager
Maurice Franceschi
Project Sponsor
Graham Venters
Current Stage
Close
Status
Withdrawn
Start Date
24-Apr-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Nov-2013
Programme Priority
1
Overall Priority
Normal
Category
Compliance