The current PG Open Day and Tours booking forms are currently located on the 'praline' server, which needs to be decommissioned as it is not supported. There are also security issues with the current implementation, which is not correctly protected.
The scope of this project is to migrate the redeveloped booking systems for PG Open Day and Tours and their administration interface to the LAMP server provided by IS.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
April 2014 | BLUE | 42.5 days | 43.3 days | 0.6 |