Organisation
Work/Task Breakdown and 3 point Estimates
3point estimates (Best case-Most likely-Worst case): 13-20-37 days Estimate with 95% confidence: 29 days
Breakdown per team:
1. Dev Tech
-Infrastructure set up: 2-3-6 days -TAD: 1-2-3 -Load Testing 2-3-6 -Support for the process 2-3-6
2. Dev Team
-Deploy to Dev 0.5-1-1 -UAT 1-2-6 -SDD/Implementation: 0.5-1-2
3. Production
Handover and deployment:
-Apps Man 0.5-0.5-1 days -Tech Man 0.5-0.5-1 days
4. Project Services
-manage projects and reporting 3-4-5 days