Organisation

 

Work/Task Breakdown and 3 point Estimates

3point estimates (Best case-Most likely-Worst case): 13-20-37 days  Estimate with 95% confidence: 29 days

Breakdown per team:

1. Dev Tech 

-Infrastructure set up: 2-3-6 days -TAD: 1-2-3  -Load Testing 2-3-6  -Support for the process 2-3-6 

2. Dev Team 

-Deploy to Dev 0.5-1-1  -UAT 1-2-6  -SDD/Implementation: 0.5-1-2  

3.  Production

Handover and deployment:

-Apps Man 0.5-0.5-1 days  -Tech Man 0.5-0.5-1 days 

4. Project Services

-manage projects and reporting 3-4-5 days

Project Info

Project
Open Days and Tours Migration
Code
STU233
Programme
Student Services (STU)
Project Manager
Franck Bergeret
Project Sponsor
Rebecca Gaukroger
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
26-May-2014
Programme Priority
2
Overall Priority
Normal
Category