August 2013
- Report Date
- August 2013
Achievements in last period
- Brief signed off
- Migration to Dev completed
Issues
n/a
Next Steps
- Migration to Test
- sign off User testing (UAT) and Acceptance stage
- Migration to Live
Milestones
6-Sep-2013 | Migration to Test completed |
12-Sep-2013 | Migration to Live completed |
26-Sep-2013 | Deployment Sign Off |
04-Oct-2013 | Close |
- Approved budget
- 29.0 days
- Activity this month
- 8.4 days
- Activity this year
- 8.4 days
- Activity to date
- 10.5 days
- Estimate to complete current year
- 18.1 days
- Estimate to complete future years
- 0.0 days