August 2013

Report Date
August 2013

Achievements in last period

  • Brief signed off
  • Migration to Dev completed

Issues

n/a

Next Steps

  • Migration to Test
  • sign off User testing (UAT) and Acceptance stage
  • Migration to Live

Milestones

6-Sep-2013Migration to Test completed
12-Sep-2013Migration to Live completed
26-Sep-2013Deployment Sign Off
04-Oct-2013Close

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
29.0 days
Activity this month
8.4 days
Activity this year
8.4 days
Activity to date
10.5 days
Estimate to complete current year
18.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Open Days and Tours Migration
Code
STU233
Programme
Student Services (STU)
Project Manager
Franck Bergeret
Project Sponsor
Rebecca Gaukroger
Current Stage
Close
Status
Closed
Start Date
05-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
26-May-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance