February 2014
- Report Date
- February 2014
Achievements in last period
- Funding agreed for post live fixes
- Post Live fixes built as per issue raised. Ready for deployment to Test
Issues
n/a
Next Steps
- Test post live fixes and close
27-Mar-2014 | Post Live fix |
24-Apr-2014 | Close |
- Approved budget
- 42.5 days
- Activity this month
- 2.1 days
- Activity this year
- 36.3 days
- Activity to date
- 38.4 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days