April 2014
- Report Date
- April 2014
Achievements in last period
- Fixed issue with Test Access: load balancer fixed. Final user testing can now progress
Issues
- PG Open Day application has now been tested and signed off by users. Remaining outstanding test is one jira related to the Tours. Delay caused by unavailability of staff in SRA. No further dev work expected (it has been tested ok by Dev Services in Test). Last task is to deploy post live fixes.
Next Steps
- Complete testing of Tours and close
22-Apr-2014 | Post Live fix |
29-Apr-2014 | Close |
- Approved budget
- 42.5 days
- Activity this month
- 1.7 days
- Activity this year
- 43.3 days
- Activity to date
- 43.3 days
- Estimate to complete current year
- 0.6 days
- Estimate to complete future years
- 0.0 days