Organisation
Work/Task Breakdown
Plan
Produce Project Brief and Plan
Check if any active projects run in PUBS DEV
Agree testing with End users
Do It
Set up DEV environment
Migrate DEV to new infrastructure
Follow-up tasks to DEV migration
Update TAD & Migrations Wiki
Set up TEST environment
Migrate TEST to new infrastructure
Follow-up tasks to TEST migration
Update TAD & Migrations Wiki
Check It
Carry out user testing and report any testing issues
Respond to any testing issues
Deployment checklist
Release
Set up LIVE environment
Migrate LIVE to new infrastructure
Follow-up tasks to LIVE migration
Update TAD & Migrations Wiki
Initial user testing of related applications
Production Hand-over
Close
Prepare closure documentation and submit to WIS
Resources, Skills and Costs
The project is estimated to require 31 days effort by IS Applications. This has been broken down as follows:
Plan it:
Project Services (2 days)
Applications Management (0.5 day)
Development Technology (0.5 days)
Do it:
Development Technology (14 days)
Project Services (3.5 days)
Check it:
Development Technology (0.5 day)
Applications Management (0.5 day)
Release:
Development Technology (5.5 days)
Applications Management (0.5 day)
QA and Sign-offs:
Project Services (1 day)
Development Technology (1 day)
Applications Management (1 day)
Close:
Project Services (0.5 day)