Organisation - follow on project

 

Work/Task Breakdown

 

Business Analysis

Establish requirements for data feed

Map CARS data to CareerHub

Analysis of legacy systems/universes

 

Build (Infrastructure)

Prepare TAD

Review/Sign off TAD

Order servers through ITI

Build of web & database servers

 

Build (Development)

Analyse/design SSO solution

Design student feed

Sign-off design documentation

Build student data feed

Build SSO solution

Create database views for provisioning

Peer Testing

 

Build (Joint)

System Documentation - TAD & Ops Doc

System Documentation - data feed

Handover to Production (inc.Deployment Checklist)

Sign-off build

 

Testing

Deploy feed, views and SSO to Live

Pre-Live testing

Support vendor testing

Sign-off testing

 

Deployment

Make changes to MyEd

Set up CareerHub on Web Server

Implement provisioning mechanism

Migrate required data from CARS to CareerHub

Support deployment to Live

Decommission applications & CARS databases

 

Resources, Skills and Cost

The effort on this project has been estimated at 51 days to achieve the stated objectives. This has been broken down as follows:

 

Business Analysis

Project Services - 1.5 days

 

System Design

Development Technology - 5.5 days

Development Services - 1 day

Production Management - 1 day

 

Build

Development Technology - 9 days

Development Services - 6 days

Production Management - 2 days

Service Management - 1 day

 

Integration

Development Technology - 3 days

Development Services - 1.5 days

Production Management - 1.5 days

 

Deployment

Production Management - 4 days

 

Closure

Project Services - 1 day

 

Project Management

Project Services - 11 days

 

Quality Assurance

IS Applications - 2 days

 

Resources for the tasks to be done by Development Technology have been secured through to the Build stage; resources in Development Services are still under discussion (as at 10/06)

Project Info

Project
New Careers System Options Evaluation
Code
STU241
Programme
Student Services (STU)
Project Manager
David Watters
Project Sponsor
Ruth Donnelly
Current Stage
Close
Status
Closed
Start Date
02-May-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2014
Programme Priority
2
Overall Priority
Normal