Organisation - follow on project
Work/Task Breakdown
Business Analysis
Establish requirements for data feed
Map CARS data to CareerHub
Analysis of legacy systems/universes
Build (Infrastructure)
Prepare TAD
Review/Sign off TAD
Order servers through ITI
Build of web & database servers
Build (Development)
Analyse/design SSO solution
Design student feed
Sign-off design documentation
Build student data feed
Build SSO solution
Create database views for provisioning
Peer Testing
Build (Joint)
System Documentation - TAD & Ops Doc
System Documentation - data feed
Handover to Production (inc.Deployment Checklist)
Sign-off build
Testing
Deploy feed, views and SSO to Live
Pre-Live testing
Support vendor testing
Sign-off testing
Deployment
Make changes to MyEd
Set up CareerHub on Web Server
Implement provisioning mechanism
Migrate required data from CARS to CareerHub
Support deployment to Live
Decommission applications & CARS databases
Resources, Skills and Cost
The effort on this project has been estimated at 51 days to achieve the stated objectives. This has been broken down as follows:
Business Analysis
Project Services - 1.5 days
System Design
Development Technology - 5.5 days
Development Services - 1 day
Production Management - 1 day
Build
Development Technology - 9 days
Development Services - 6 days
Production Management - 2 days
Service Management - 1 day
Integration
Development Technology - 3 days
Development Services - 1.5 days
Production Management - 1.5 days
Deployment
Production Management - 4 days
Closure
Project Services - 1 day
Project Management
Project Services - 11 days
Quality Assurance
IS Applications - 2 days
Resources for the tasks to be done by Development Technology have been secured through to the Build stage; resources in Development Services are still under discussion (as at 10/06)