Work/Task Breakdown
Reach agreement on SLA and terms & conditions to determine scale of work required by IS Applications
List tasks to be done by IS Apps staff
Discuss and obtain estimates for the necessary work
Produce a formal estimate for the implementation of CareerHub
Prepare a project plan for the implementation of CareerHub
Work with the relevant resource managers to determine when work can be scheduled
Consult with business partners to obtain agreement on plan
Write up agreed estimates and project plan
Prepare project brief and circulate for discussion
Obtain sign-off from stakeholders and submit to WIS
Resources Skills and Cost
The effort on this project has been estimated at 10 days to achieve the stated objectives. The work will mainly use project management skills, with relevant input from colleagues in Production Management and Development Technology, as well as our business partners who are stakeholders, and CareerHub.
It should be noted that, to date, 2 days effort has been used in preliminary discussions (across IS Apps) about this project and that this total has been recorded against the 10 day budget.