Report for May 2014
- Report Date
- May 2014
Achievements in Last Period
- Project brief prepared and submitted to WIS
- Draft plan & estimates prepared for Careers
- SLA revised and sent to vendor for feedback
Issues
- Business partners have not yet signed off draft documentation
- Vendor not yet signed off SLA
Next Period
- Project deliverables to be submitted to WIS
- Follow on project to be opened
- Project to be closed
Milestones
06-Jun-2014 | Project closure | Close |
06-Jun-2014 | Delivery Milestone | Deliver |
- Approved budget
- 10.0 days
- Activity this month
- 7.5 days
- Activity this year
- 9.5 days
- Activity to date
- 9.5 days
- Estimate to complete current year
- 0.5 days
- Estimate to complete future years
- 0.0 days