Report for June 2014

Report Date
June 2014

Achievements in Last Period

  • Estimates finalised & project plan prepared
  • Brief for follow-on project prepared and submitted to WIS
  • SLA signed off
  • Project closure submitted to WIS

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
10.0 days
Activity this month
0.5 days
Activity this year
10.0 days
Activity to date
10.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New Careers System Options Evaluation
Code
STU241
Programme
Student Services (STU)
Project Manager
David Watters
Project Sponsor
Ruth Donnelly
Current Stage
Close
Status
Closed
Start Date
02-May-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
16-Jun-2014
Programme Priority
2
Overall Priority
Normal