Report for September 2018

Report Date
September 2018

Achievements this period

Technical issues with Funnelback search engine have not been overcome and the use of Funnelback has been reviewed and removed from the solution.

Whilst this is a significant change to the overall technical solution, alternative products are under consideration to achieve the desired search functionality.

A revised design and proof of concept using the alternative products will be built and available for mid-October. 

Development Services resource have confirmed that in the event that changes are required to the search widget, these could be accommodated during November.

With the data challanges with Pure profiles and the inconsistencies across Schools EdWeb profiles,  the search results currently returned are profiles showing academic areas of expertise rather than Pd.D specifics.  Until data quality and API capability are proven search results are an overestimated guess of academics that may or may not be willing to supervise. These results are not be suitable for a prospective student journey. Until there is a fit for purpose staff database there would be not appetite to deploy the search tool at this time.

Student Recruitment  are not in a position to drive data and standards development across the schools and are very much on the periphery of being able to influence change in this area.  Profile guidance is owned by the schools and this differs widely across the schools.  This coupled with the fact that different process for dealing with Ph.D enquiries makes it difficult to agree, across the university any consistent process or guidance at this time. 

To keep the momentum going the project would like to understand what developments have taken place in this space within Service Excellence Programme.  

This project also has synergies  with emerging developments in EDWeb and its wider adoption and a view of that roadmap needs to be factored into the development of this service. 

Issues

  • None

Next steps

  • Design and build proof of concept with alternative search products
  • Engage with Service Excellence to understand developments in this space
  • Understand any specific guidelines for Pure in the University
  • Understand the roadmap for EdWeb

Milestones

Target Datesort descending Previous Date Title Stage Complete
31-Aug-2017  30-Jun-2017 End of Planning Plan Yes
05-Feb-2018 No date available       Unsuspend project and Kick off the development work Execute No
11-May-2018 23-Mar-2018 End of Planning (re-plan following suspension) Plan Yes
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
31-Oct-2018 No date available Deployment Deliver No
16-Nov-2018 No date available Project Closure Close No
         
External Milestones        
21-Dec-2018 21-Dec-2017 Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available"         
21-Dec-2018 11-May-2017 Guidance policy for use and tagging of keywords to support PGR search
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
1.3 days
Activity this year
4.3 days
Activity to date
4.3 days
Estimate to complete current year
15.7 days
Estimate to complete future years
0.0 days

Project Info

Project
PGR Opportunity Finder
Code
STU253
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Jane Johnston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
23-Jun-2016
Planning Date
11-May-2018
Delivery Date
08-Feb-2019
Close Date
28-Feb-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary