Report for April 2018

Report Date
April 2018

 

Achievements This Period

  • Build on  TEST completion.
  • Test Plan and scenarios completion.

  • Integration milestone completion.

  • UAT completed.

  • Closed RISKS 
  • Deployment to LIVE 26th April 2018.

Issues

  • None

Next Steps

  • Delivery Milestone approval at WIS.
  • Closure Preparation.

 

Milestones

 

 Target Datesort descending  Title
 25-May-2018  Project Delivery
 08-Jun-2018  Deployment sign-off Milestone
 15-Jun-2018  End of Project Closure Stage
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
59.0 days
Activity this month
11.0 days
Activity this year
40.0 days
Activity to date
40.0 days
Estimate to complete current year
19.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Freedom of Information GDPR Updates
Code
STU259
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Sara Cranston
Current Stage
Close
Status
Closed
Start Date
31-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2018
Programme Priority
3
Overall Priority
Higher
Category
Compliance