Report for June 2018

Report Date
June 2018

 

Achievements This Period

 

  • Closure report approved

  • project closed

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
59.0 days
Activity this month
2.0 days
Activity this year
48.0 days
Activity to date
48.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Freedom of Information GDPR Updates
Code
STU259
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Sara Cranston
Current Stage
Close
Status
Closed
Start Date
31-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Jun-2018
Programme Priority
3
Overall Priority
Higher
Category
Compliance