Impact

Priority and Funding

  • Priority 3 (normal)
  • Core

Initial Cost Estimates

Exact external costing will depend upon the product purchased and any specific configuration work required.  Of the 3 solutions under investigation at present the most expensive quote provided is:

External spend :

Cost Element 2019/20 2020/21 2021/22 2022/23
Software licence costs (Inc Vat) £12,600 £12,600 £12,600 £12,600
Other supplier costs (Inc Vat) £17,600      
Total £30,200 £12,600 £12,600 £12,600

The solution is being purchased as a SaaS (Software as a Service) via the G-Cloud 11 framework on the Digital Marketplace.  The application will be hosted remotely rather than on site.  As a result it is expected that post implementation support costs will be kept to a minimum.  As part of the service initiation an OLA will be required between Records Management and Production Management.  This will cover the on-going internal support of the project along with any related internal support costs.

Impact and Dependencies

  • The present version of ColdFusion solution has a technical end of Life as of May 2019.
  • The project effort has been assigned as follows:
    • Financial year 2018/19 - 30 days
    • Financial year 2019/20 - 70 days
  • The procurement of the product will include an element of training for the Records Management team.  There may also be the need for a wider training/communication programme for the various individuals across the University, external to Records Management, who are requested to contribute to FoI responses.  

Project Risks

Ref: Risk Description Initial Risk Current Risk Status Management Approach Risk Owner
1 Product evaluation. Green Green Open Reduce Anne Grzybowski
2 Resource availability - Records Management Green Green Open Reduce Anne Grzybowski
3 Resource availability - IS Green Green Open Reduce Ken Miller
4 Funding only available in 2018/19 Green Green Closed Avoid Ken Miller
5 Change of Procurement contact Green Green Closed Retain Ken Miller
6 No funding available for system purchase Amber Amber Closed Remove Tracey Slaven
7 Days assigned to 2019/20 insufficient Green Green Open Reduce Ken Miller
8

Historic data migration may prove more complicated than estimated for

Amber Amber Open Reduce Ken Miller
9

Availability of Development Services representative

Green Green Open Reduce Bill Lee

Project Info

Project
G-Cloud replacement of FOI Request planning tool
Code
STU265
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Leigh Chalmers
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
22-Mar-2019
Planning Date
19-Apr-2019
Delivery Date
28-Feb-2022
Close Date
01-Jul-2022
Overall Priority
Normal
Category
Compliance