Work/Task Breakdown
- Produce G-Cloud procurement short list of preferred suppliers.
- Document product evaluation criteria.
- Carry out hands on evaluation of solution via:
- Supplier led online demonstration
- Hands on evaluation using evaluation environment
- Technical evaluation regarding single sign on integration
- Procurement and implementation of preferred solution.
- Analysis of data held in existing ColdFusion management database and migration to identified solution
- Once completed agree decommissioning of initial ColdFusion system.
Resources, Skills and Costs
The project will require input from the following stakeholders:
- Project Sponsor
- Project Manager
- Senior User/Business Lead
- Business Analyst
- Development Technology
- Software Development
- Enterprise Architecture
Project Governance
- Regular communication with Records Management to co-ordinate evaluation, procurement and implementation tasks.
- Regular stakeholder communication on project progress by email.
- Formal approval accepted from stakeholders via email/project meeting minutes.
Project Stakeholders
Name | Business Area | Role |
---|---|---|
Alex Carter | Service Management | SENIOR SUPPLIER |
Ken Miller | Project Services | PROJECT MANAGER |
Anne Grzybowski | Records Management | PROJECT TEAM - Information Compliance Manager |
Ann-Marie Noble | Records Management | PROJECT TEAM - Information Compliance Manager, Business Lead |
Bill Lee | Development Services | PROJECT TEAM - Development Team Manager |
David Creighton-Offord | IS Applications | PROJECT TEAM - Data Security Analyst |
Dave Berry | Enterprise Architecture | Enterprise Architect |
Elaine Wighton | IS Applications Project Services | PROJECT TEAM - Business Analyst |
Alison Johnson | Procurement | PROJECT TEAM - Procurement advisor |
Jim McGeorge | USG | Acting Portfolio and Programme Owner |
Jamie Thin | IS Applications Project Services | Programme Manager |
Mark Lang | Is Applications Development Technology | PROJECT TEAM - Development Technology Team Manager |
Suran Perera | Production Management | Applications Service Group Team Manager |
Tracy Slaven | GaSP | PROJECT SPONSOR |
Project Estimations
This project has been estimated at 100 days. However, as the solution is as yet unknown, the project will require to be re-estimated at the end of the evaluation phase
The current project estimate can be viewed here:
Attachment | Size |
---|---|