Report for May 2022
- Report Date
- May 2022
Achievements
- Decommission Process underway, final tasks with DevTech to complete
- On-going support provided to Records Management team after the eCase go-live
- Closure Report signed off by most stakeholders
Issues
- Still need Production Management signoff before closure
Next Steps
- Complete decommission of ColdFusion FOI system
- Close project
- Approved budget
- 170.0 days
- Activity this month
- 1.1 days
- Activity this year
- 16.4 days
- Activity to date
- 173.2 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days