Organisation

Work/Task Breakdown

D1. A diagram describing the existing system architecture, business processes, users, data (including flows) and security

  • Analysis of existing processes
  • Analysis of existing content, including use of personal data
  • Analysis of existing security
  • Write up of high level summary document
  • Review and approval of document by project stakeholders

D2. A product vision statement

  • Analysis of existing issues / problem statement
  • Development of goal (and vision) statement

D3. A high level business requirements document summarised by category and priority

  • Requirements sessions/workshops
  • Write up of sessions/workshops
  • Write up of business requirements document
  • Review and approval of document by project stakeholders

D4. An options summary document to include pros, cons, risks and indicative costings

  • Discussions with internal subject matter experts on software development / re-development
  • Analyse do nothing / do 'something' options to look at potential risks including security risk and product failure
  • Analyse EdWeb option with Drupal 7 (existing) and Drupal 9 (future)
  • Analyse opportunities in market and best practice from websites and other institutions and organisations

Resources, Skills and Costs

  • Project Sponsor and Deputy Director, Marketing, Communications and Marketing
  • Project Manager, IS Applications
  • Business Analyst, IS Applications
  • Business Lead and Head of Digital Marketing, Communications and Marketing
  • Business Lead and Head of Student Recruitment Web Content
  • Senior Supplier and Head of Project Services, IS Applications
  • Head of Production Management, IS Applications
  • Software Developer, IS Applications
  • Information Security

Project Governance

  • Project team meetings - project progress and clarifications
  • Escalations to project sponsor and senior supplier, where required
  • Stage gates and sign-offs to move through major milestones - Planning, Delivery and Closure
  • Alignment with SEP programme, where required - Student Recruitment and Admissions strand

Project Stakeholders

Name Business Area Role
Adrian Richardson Development Services, IS Applications Subject Matter Expert - Software Development
Alastair Fenemore Information Security Chief Information Security Officer
Ben Armstrong (Project Team Member) Project Services, IS Applications Project Manager
Dave Berry Enterprise Architecture, IS Applications Enterprise Architect
Elaine Wighton (Project Team Member) Project Services, IS Applications Business Analyst
Gary Van Breda (Project Team Member) Development Services, IS Applications Software Developer
Mark Ritchie Project Services, IS Applications Senior Supplier and Head of Project Services
Neil Allison (Project Team Member) Communications and Marketing Business Lead and Head of Student Recruitment Web Content
Niall Bradley (Project Team Member) Communications and Marketing Project Sponsor and Deputy Director, Marketing
Stefan Kaempf Production Management, IS Applications Head of Production Management
Steven Ross (Project Team Member) Communications and Marketing Business Lead and Head of Digital Marketing
Stratos Filalithis Website and Communications Head of Website & Communication Technologies

Project Estimations

35 days - IS Applications

For further details, please refer to the attached Three Point Estimate

stu266_three_point_estimate.xls

 

Project Info

Project
UG & PG Degree Finder Options Appraisal
Code
STU266
Programme
Student Services (STU)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Niall Bradley
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Sep-2019
Planning Date
20-Sep-2019
Delivery Date
31-Jan-2020
Close Date
06-Mar-2020
Overall Priority
Higher

Documentation

Plan